INSTALLATION

All the "left", "right", "front" and "rear"
designations in this manual are as viewed by
the operator facing the control console.

LOCATION

1.
The floor area required by the standard machine is
111 inches (2819.4 mm) in width by 82.50 inches
(2095.5 mm) in length. Machine height (with the saw
head fully raised) is 90.00 inches (2286.0 mm). Refer
to pages 1 thru 4 for further machine dimensions.
2.
Locate the machine to provide sufficient clearance
for: (a) Material loading and unloading; (b) All
door openings; (c) Head elevation; (d) Chip
conveyor removal; (e) Maintenance and lubrication
procedures; (f) Operation of the any supplied
machine accessories.
3.
Accessories such as roller stock conveyors will
require additional work area.

OSHA NOTICE!!

OSHA Regulation 1910.212 (5B).
Machines designed for a fixed location shall
be securely anchored to prevent walking or
moving.

UNPACKING

1.
The machine is fastened to and shipped on a wooden
skid. Overseas shipments are also crated.
2.
Remove all protective covers, strapping, crating,
etc. Then: (a) Remove all bolts which fasten the
machine to the shipping skid; (b) Do not remove
the shipping bracket that attaches the saw
head to the vise base yet; (c) Remove any loose
boxed items that may have been placed on the
vise bed; (d) Inspect the machine and all parts for
shipping damage. Claim procedures are listed on
this manual's inside front cover.

CLEANING

1.
If necessary, use solvent to remove rust-preventive
coating applied to exposed bare metal surfaces for
shipping purposes.

LIFTING

NEVER lift the machine by its sawing head.
1.
Four (4) permanent eye holes are provided for
machine lifting purposes: (a) Two (2) lifting eyes
are located at the rear of the index vise roller table;
(b) Two (2) other lifting eyes are located on the
machine's front left and right corners.
2.
Using chains attached to the lifting eyes, it is
recommended that lifting and transporting of the
machine be done with an overhead hoist. Net weight
is approximately 6800 pounds (3084.5 kg).
It is recommended to protect painted surfaces from
damage due to the lifting chains coming into contact
with machine surfaces.
3.
Roller stock conveyors (if supplied as optional
equipment) can be lifted and transported by
overhead hoist, fork lift, or by other means that
provides adequate safety precautions.

FLOOR INSTALLATION

1.
Thread the provided leveling screws into the
machine base mounting holes and attach the jam
nuts. Position the provided foot castings under the
leveling screws.
2.
Place a machinist's level on the machined yoke
surface (remove the cover) and the fixed vise guide
rails. Adjust the leveling screws until the machine
is level and weight bears evenly on all mounting
pads.
Leveling the Machine.
7