Tests
10.3

Daily testing with the test rod

SOLID-2SF Multiple Light Beam Safety Devices are subjected to cyclical testing.
Nevertheless it is very important to check the protective field for its effectiveness every day,
so as to ensure that the protection stays effective at every point of the protective field after
a parameter or tool change.
Only use an appropriate test rod with ∅ 30 mm (accessory), and NEVER use your fingers,
hand or arm for checking the system!
a = Test start
Picture 10.1:Testing the protective field with the test rod
 The LED1 of the Receiver must be observed during the testing procedure. If a beam is
interrupted by the test rod, this LED1 must change from "green" to "red".