7.4.3.3.1 Grid-tied Point Control

Procedure
Step 1 On the Operation console screen, choose Device maint > Energy control > Grid-tied point
control and perform the corresponding operation.
Figure 7-23 Grid-tied point control
Table 7-3 Description of control mode parameters
Parameter
Control mode
Issue 02 (2017-12-12)
Description
If this parameter is set to
Default, the SUN2000L
output power is not limited.
The SUN2000L can export
its rated power to the power
grid.
If this parameter is set to
Grid connection with zero
power and the SUN2000L
is connected to a power
meter, the output power of
the SUN2000L is supplied
only to the local load, but
not the power grid.
If this parameter is set to
Power-limited Grid
Connection and the
SUN2000L is connected to a
power meter, the
SUN2000L supplies power
limited based on the setting
of Grid-tied Point Power
to the power grid. The time
for power-limited grid
connection precision is 3s.
The precision is [-3%Pmax,
0].
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
7 Operations on the Local FusionHome App
Value Range
Default
Grid connection with
zero power
Power-limited Grid
Connection
77