Bypass Operation: Load Power Supplied Through Ups Internal Static Bypass Line; Figure 3-2 Single Line Diagram - Bypass Operation: Load Fed Through Static Bypass Line - Toshiba G9000 SERIES Installation And Operation Manual

480/480 v 100/160/225/300/500/750 kva
Hide thumbs Also See for G9000 SERIES:
Table of Contents

Advertisement

In the event of a UPS module failure during Parallel Operation, the critical load power will be
continually supplied and shared by all other UPS.
!
NOTE
3.2.2

Bypass Operation: Load Power supplied through UPS internal static bypass line.

CB
Bypass
Input
User supplied
MCCB
CB
AC
Input
User supplied
MCCB
CB2
External
Battery
Cabinet
Battery
Figure 3-2 Single Line Diagram – Bypass Operation: Load fed through static bypass line.
Figure 3-2 shows the Internal Bypass line is a Hard-wired line through 52S which supplies the critical
load with unconditioned bypass input power. Upon switching to the Internal Bypass line, the Static Transfer
Switch line through CB3 (herein after STS contactor CB3) supplies the power immediately, and then the
Internal Bypass line through 52S supplies the power. In the event of a switching to the Bypass line, the
power to the critical load will be uninterrupted. The purpose of this Internal Bypass line is to route power to
the critical load while the UPS module is de-energized (converter and inverter), and during Start-up before
the system is fully operational.
Each UPS internal static bypass line will equally share the power supplied to the critical load
whenever the system is in the Parallel Operation.
Phone: 800.894.0412 - Fax: 888.723.4773 - Web: www.clrwtr.com - Email: info@clrwtr.com
The Bypass Input breaker and cables are to be supplied and installed by the user or the
constructor. (See WARNING 4 on page 5)
CONVERTER
CB1
CHARGER
UPS Module
52S
CB3
Static Transfer
Switch
INVERTER
52C
Power Flow
Not in Use
CB
Output