OPERATOR CONTROLS AND INDICATORS

The G9000 Series operator controls and indicators are located as follows (Door exterior):
8
3
2
1
7
4.1

LED DISPLAY

1) Load on inverter [ LOAD ON INVERTER ] (green)
Illuminates when power is supplied from inverter to the critical load.
(Indicates the state of inverter transfer switch "52C".)
2) Battery operation [ BATTERY OP. ] (orange)
Illuminates when power is supplied from batteries following a power failure.
3) Load on bypass [ LOAD ON BYPASS ] (orange)