4.10.5 Verify Lightning and Grounding Protection
Ensure that all equipment lightning protection and grounding protection measures have
been taken. Information about the protection measures is covered in
and Lightning Protection" and
should be inspected before proceeding to weatherproof the connections.
4.10.6 Weatherproof all Connections
Once testing is completed successfully, you will need to seal and weatherproof the connection
points by wrapping them with all-weather electrical tape and mastic tape, as illustrated in
Figure 4-22. At least 3 layers of tape are needed, making sure that the wrapping direction of
the last layer is from the bottom up. The last layer should be tight enough to keep from
cracking.
Figure 4-22: Weatherproofing Example
section 4.10.2
"Grounding Protection". All protection points
34
section 3.9
"Grounding