2.4
Personnel Requirements
The installation personnel must master the basic safe operation knowledge, through the
training, and having the corresponding qualifications.
2.5
Against Lightening and Grounding Protection
CAUTION
:
It is unlikely to happen but since the LTE base station is very sophisticated
equipment so we would recommend you to test it on the ground to make sure
everything is functioning before install on the tower.
The operator must prepare external against lightning protector to protect the GPS,
external antenna and RJ-45 port.
Grounding Notes:
The ground wire adopts yellow-green wire that is no smaller than 16 mm² .
Grounding principle: as near as possible.
The base station connects to the reliable outdoor grounding point (earth) through
one ground screw.
The connection of the grounding points and the ground bar need to be tight and
Figure 2-1 Installation Space Requirement
9