C. Mantel and Wall Projections

WARNING! Risk of Fire! Comply with all minimum clear-
ances as specified. Framing closer than the minimums list-
ed must be constructed entirely of non-combustible materi-
als (i.e., steel studs, concrete board, etc.).
Note: Measurement is taken from top of the
opening, NOT the top of the fireplace.
Combustible Mantels
COMBUSTIBLE MANTEL
10 mm
THICK WALL
SHEATHING
14 IN. (356 mm) MIN. BOTTOM OF
MANTEL TO TOP OF APPLIANCE
OPENING
Figure 10.3 Clearances To Combustibles Mantels Or Other
Combustibles Above Appliance
46
12 IN. MAX.
(305 mm)
APPLIANCE OPENING
Heat & Glo • SLR-X-AU Installation Manual • 2493-980 Rev. B • 12/17
Non-combustible Mantels
10 mm
THICK WALL
SHEATHING
NON-COMBUSTIBLE
6 IN. MAX.
(152 mm)
COMBUSTIBLE
MANTEL
Figure 10.4 Clearances To Non-Combustible Mantels Or Other
Non-Combustibles Above Appliance
12 IN.MAX.
(305 mm)
MANTEL
14 IN. (356 mm) MIN. BOTTOM OF
MANTEL TO TOP OF APPLIANCE
OPENING
NON-
APPLIANCE OPENING

Advertisement