Activation

Machine working conditions

Keep the conditions of the manufacturer for machine operating! If recommendations
are not kept, damage can occur to the machine.
The manufacturer warrants the correct function of the machine for these
conditions:
At temperature air from 5°C to 40°C, the temperature average during 24 hours
must not exceed over 35°C.
At relative dampness of the air in the extend from 30% to 95% (not concentrate).
Altitude lower than 1000 metres.
Do not expose the machine to the radiation (for example microwave radiation,
ultra-violet radiation, laser radiation, x-ray radiation). Radiation can cause problems
with the machine function and deteriorating condition of the isolation.

Band saw unpacking and assembling

Remove the packing from the machine and unpack all parts.
Attention!
Switch off the main switch and lock it, before you start
assembly! Otherwise, there is possibility of hazardous machine
starting.

Machine installing and levelling

Check the floor supporting capacity before machine installing. If the floor capacity does
not agree with requirements, you must prepare the necessary base for the machine.
Minimal requirement:
Machine weight – Practix 285.230 G
+ Weight of accessories
+ Maximum weight of material
The machine must be levelled at the horizontal position. All feet of the machine
must touch with the floor after levelling.
The machine must be levelled by means of the calibrated spirit level. Spirit level is
put on the vice area. Set the roller conveyors according to the spirit level.
For machine levelling, take care that there is sufficient available space for
operation, repair work, servicing of the machine and handling the material.
The machine including appended parts and accessories must be visible from the
place of operation.

Machine disposal after lifetime

Blown out all service fluids (cooling liquid, hydraulic oil) into designated reservoir.
Dismantle machine into separate parts and dispose them in accordance with valid
directives.

Electrical connection

Only a qualified professional must carry out the servicing
and repairs of the electric equipment! Take special care
during work with electrical equipment. High voltage shock can
have fatal consequences! Always keep notes about work safety!
Manual 215 kg / Pulldown 225 kg