Installation
The enclosure and mounting brackets of the PTP 500 Series Bridge product range are capable of
withstanding wind speeds up to 151mph (242kph). The installer should ensure that the structure
the bridge is fixed to is also capable of withstanding the prevalent wind speeds and loads. See
Section 12
"Wind Loading".
The integral safety loop should be used both for hoisting the ODU up a mast or building and into
position, and also as a fixing point to secure a permanent safety lanyard from the tower/building
to the ODU in case of mounting failure.
Figure 16 Integral Safety Loop
The length of the safety lanyard must not exceed 1m (approx 3 ft) in length. The lanyard should
be made from a material that does not degrade in an outdoor environment.
The safety lanyard must be fixed to a separate fixing point that is not part of the direct mounting
system for the ODU.

7.7 Connecting Up

7.7.1 Preparing the PIDU Plus To ODU Cable

NOTE: The maximum cable length between the ODU and the user's Network Equipment is 100m
(330 ft). Cable lengths up to 300m (984 ft) can be used where the PIDU Plus to ODU cable is
supplying power only, i.e., when using the PTP 500 Series Bridge Optical Interface.