Installation
3. Installation
3.1 General
The machine must be installed by authorised personnel only.
Read these instructions through carefully as they contain important information
regarding correct installation.
The instructions should be used together with the machine's wiring diagram and
flow diagram.
The machine is CE-marked. The CE-mark is only valid for the machines with the
original design. If the machine is damaged as a result of the instructions not being
followed, the supplier guarantee and product liability ceases.
3.2 Requirements for installation on site
3.2.1 Lighting
In order to ensure the best possible working conditions during installation, opera-
tion, service and maintenance, make sure that the machine is installed in a well-
lit room.
3.2.2 Ventilation
The machine generates heat and steam when in operation. For a good working
environment, a certain air change rate is required in the washing room. The ven-
tilation requirements for the room are dimensioned as per applicable standars.
3.2.3 Drain
There must be a floor drain with an effective trap for the machine's waste water
and for water used for cleaning. The floor drain capacity can be found in the
TECHNICAL SPECIFICATIONS.
3.2.4 Service space
A 1-metre free space should be allowed in front of the machine for service pur-
poses.
WD-4C