Commissioning - GE T60 Instruction Manual

Ur series
Hide thumbs Also See for T60:
Table of Contents

Advertisement

1 GETTING STARTED
Tables for recording settings before entering them via the keypad are available from the GE Multilin website at
www.GEmultilin.com. Commissioning tests are also included in the Commissioning chapter of this manual.
The T60 requires a minimum amount of maintenance when it is commissioned into service. Since the T60 is a microproces-
sor-based relay, its characteristics do not change over time. As such, no further functional tests are required.
Furthermore, the T60 performs a number of continual self-tests and takes the necessary action in case of any major errors
(see the Relay Self-Test section in Chapter 7 for details). However, it is recommended that T60 maintenance be scheduled
with other system maintenance. This maintenance may involve the in-service, out-of-service, or unscheduled maintenance.
In-service maintenance:
1.
Visual verification of the analog values integrity such as voltage and current (in comparison to other devices on the cor-
responding system).
2.
Visual verification of active alarms, relay display messages, and LED indications.
3.
LED test.
4.
Visual inspection for any damage, corrosion, dust, or loose wires.
5.
Event recorder file download with further events analysis.
Out-of-service maintenance:
1.
Check wiring connections for firmness.
2.
Analog values (currents, voltages, RTDs, analog inputs) injection test and metering accuracy verification. Calibrated
test equipment is required.
3.
Protection elements setting verification (analog values injection or visual verification of setting file entries against relay
settings schedule).
4.
Contact inputs and outputs verification. This test can be conducted by direct change of state forcing or as part of the
system functional testing.
5.
Visual inspection for any damage, corrosion, or dust.
6.
Event recorder file download with further events analysis.
7.
LED Test and pushbutton continuity check.
Unscheduled maintenance such as during a disturbance causing system interruption:
1.
View the event recorder and oscillography or fault report for correct operation of inputs, outputs, and elements.
If it is concluded that the relay or one of its modules is of concern, contact GE Multilin for prompt service.
GE Multilin
Courtesy of NationalSwitchgear.com
T60 Transformer Management Relay
1.5 USING THE RELAY

1.5.7 COMMISSIONING

http://
1-19
1

Advertisement

Table of Contents
loading

Table of Contents