7.3.3

Positioning of the baffle plates

- Put the baffle plates back in place and hook them into each other
before engaging them fully in the flue way.
Follow the order of assembly shown in the diagram.
The 8-figure part number of the baffle plate is cast in the metal.
Boiler
Upper flue ways
Central flue ways
Lower flue ways
16/03/2016 - 300016839-03
8229-0010
P 420-8
P 420-9 - P 420-10
First 8229-0010 then
2 x 8229-0010
8229-0022
First 8229-0011 then
2 x 8229-0011
8229-0023
First 8229-0012 then
2 x 8229-0012
8229-0024
- Close the sweeping doors.
8229-0022
P 420-11
First 2 x 8229-0010 then
First 2 x 8229-0010 then
1 x 8229-0022
First 2 x 8229-0011 then
First 2 x 8229-0011 then
1 x 8229-0023
First 2 x 8229-0012 then
1 x 8229-0024
P 420
P 420-12
P 420-13 - P 420-14
3 x 8229-0010
1 x 8229-0022
3 x 8229-0011
1 x 8229-0023
2 x 8229-0012
2 x 8229-0012