1.2.2

Checking the project data and OS writing on GOT.

Confirm if the standard monitor OS, communication driver, option OS, project data and communication settings are
properly written onto the GOT by reading from GOT using GT Designer3.
For reading from the GOT, refer to the following manual.
1.
Select [Communication]
2.
The [Communication configuration] dialog box appears.
Set the communication setting between the GOT and the personal computer.
Click the
button when settings are completed.
3.
The [GOT Read] tab appears on the [Communicate with GOT] dialog box.
Select the [Drive information] radio button of the Read Data.
4.
Click the [Info Reception] button.
5.
Confirm that the project data and OS are written correctly onto the GOT.
1 - 12
1. PREPARATORY PROCEDURES FOR MONITORING
1.2 Writing the Project Data and OS onto the GOT
GT Designer3 Version
Screen Design Manual
[Read from GOT...] from the menu.

Advertisement

Table of Contents
loading

Table of Contents