Site Preparation
Placing the System
2-14
iCAP RQ Pre-Installation Requirements Guide (P/N BRE0009927, Revision A)
Table 2-2
lists space requirements and weights of the typical data system
hardware components. The actual values depend upon your equipment.
Table 2-2.
Typical data system space and load requirements
Module
Height [cm]
Monitor
36
Minitower
48
computer
The USB communication cables between the computer and the mass
spectrometer must be no longer than 3 m each. The workbench that
holds the data system must be located next to the workbench that holds
the mass spectrometer. For a connection length of more than 3 m, an
active hub must be placed between the instrument and the computer.
The length of the USB cable between the iCAP RQ ICP-MS
instrument and the hub is limited to 3 m, whereas between the hub and
the computer a cable length of 5 m can be used. This hub must
exclusively be used for the control of the iCAP RQ ICP-MS instrument.
Width [cm]
Length [cm]
41
18
18
43
Weight [kg]
6