Installing the SVI II AP for Double- Acting Operation

This section explains how to mount the SVI II AP for the 84/85/86 kit for double-acting valve po-
sitioner configurations.
To mount the kit:
1. Set valve to the closed position.
2. Install the mounting assembly to the yoke (Figure 14) using helical spring washer
5/16, flat washer 5/16 and hex screw 5/16-18x44.5 [1.75] LG.
NOTE
30 | =GE Oil & Gas
Kit Mount
Bracket
Figure 14 84/85/86 Actuator
Mount all components snug enough to stay in place but loose
enough to tap with rubber hammer into final position.
Lever
Rod-end