INSTALLER GUIDE
5. Insert a wall plug 'F' into each hole.
6. Place the hotbox back in position in the fireplace.
7. Fit a wood screw 'H' through each hole in the hotbox flanges and tighten to seal
the box to the fireplace surround.

10.3 Sealing floor front - All installations.

Using the floor sealing tape supplied, seal the
bottom of the hotbox to the fireplace and hearth
floor (See figure 21).
Make sure that the whole length of the front
edge of the hotbox is fully sealed.
Figure 21 Floor sealing
11. BURNER & SUPPLY PIPE INSTALLATION

11.1 Burner and supply pipe installation.

1. Refit the burner unit to the hotbox with two screws.
2. Connect the supply line to the appliance.
3. Turn on the gas supply and pressure check the installation pipe work for gas
soundness. In the United Kingdom (GB) check in accordance with the current edition
of BS 6891. In the Republic of Ireland check in accordance with the current edition of
IS 813 "Domestic Gas Installations".

11.2 Preliminary burner checks.

Some burner operations can be checked at this stage. Checking now will mean that
less disassembly will be required if any problems are found. A full check should still
be made, however, after final installation.
11.2.1 Lighting the burner.
1. If closed
open the isolating valve at the inlet elbow.
,
2. Depress the control knob and rotate it slowly anticlockwise to the 'PILOT / IGN'
position. A 'click' will be heard as the integral piezo operates. A spark should be seen
between the electrode and pilot tip.
3. Turn the control knob clockwise to the 'OFF' position. Repeat this operation until a
flame appears at the pilot. There may be a delay before the pilot lights due to air
being purged from the system. When a flame appears at the pilot keep the control
knob depressed and hold the 'PILOT / IGN' position for five seconds. When the
control knob is released the pilot flame should remain lit.
Page 29
©
Baxi Heating U.K. Limited 2011.