Setting the lift time/height of lift with the stud welding device
Step 4:
Set the gun on the workpiece and
press the trigger button on the gun
for the weld.
Make sure the green "Stud on work-
piece" control lamp lights up before
triggering.
The currently set value for the lift
time in [ms] appears on the display.
The longer the lift time, the higher
the height of lift. Determining the correct lift time requires experi-
ence and some trials. Guide values for the correct lift time can be
found in Chapter "11.1.1 Help tables for device setting" on
page 47.
The lift time is changed using the adjust-
ment ring on the welding gun for the
height of lift of the stud.
Step 5:
Make sure the device is in operating mode by selecting one of
the three functions above (green LEDs).
Notes on "Setup" mode
The setup process can be repeated as often as required. However, to avoid
the magnetic coil overheating, maintain a waiting time of approx. one second
between two test strokes.
Operating Manual Soyer Bolzenschweißtechnik
Settings
SRM
GAS
53

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ph-9 srm12Ph-3n srm

Table of Contents