Installation; External Inspections; Internal Inspections - Liebert NX User Manual

40-200kva, 480v, 60hz
Hide thumbs Also See for NX:
Table of Contents

Advertisement

2.0
I
NSTALLATION
This section describes the Liebert NX environmental requirements and mechanical considerations
that must be taken into account when planning the positioning and cabling of the UPS equipment.
Because every site is unique, this section presents a guide to general procedures and practices that
should be observed by the installing engineer, rather than step-by-step installation instructions.
WARNING
!
Do not apply electrical power to the UPS equipment before the arrival of the commissioning
engineer.
WARNING
!
The UPS equipment should be installed by a qualified engineer in accordance with the
information contained in this section.
WARNING
!
Risk of electric shock. Can cause injury and death.
Special care should be taken when working with the batteries associated with this equipment.
When connected together, the nominal battery voltage is 480VDC and is potentially lethal.
• Eye protection should be worn to prevent injury from accidental electrical arcs.
• Remove rings, watches and all other metal objects.
• Use only tools with insulated handles.
• Wear rubber gloves.
If a battery leaks electrolyte or is otherwise physically damaged, it must be replaced, stored in
a container resistant to sulfuric acid and disposed of in accordance with local regulations.
If electrolyte comes into contact with skin, the affected area should be washed immediately
with large amounts of water.
NOTE
The Liebert NX UPS can be used in TN utility system.
2.1

External Inspections

1. While the UPS system is still on the truck, inspect the equipment and shipping container(s) for
any signs of damage or mishandling. Do not attempt to install the system if damage is apparent.
If any damage is noted, file a damage claim with the shipping agency within 24 hours and contact
Emerson Network Power
claim and the condition of the equipment.
2. Compare the contents of the shipment with the bill of lading. Report any missing items to the
carrier and your local Liebert representative immediately.
2.2

Internal Inspections

1. Remove any packaging material, then visually examine the UPS and battery equipment for
transit damage, both internally and externally. Report any such damage to the shipper and to
Liebert immediately.
2. Check the nameplate inside the cabinet door to verify that the model number and rating
correspond to the ones specified. Record the model number and serial number in the front of this
installation manual. This information is necessary should service be required.
3. Check for loose connections or unsecured components in the cabinet.
4. Check for shipping damage to internal components.
®
Liebert
NX
®
Liebert Services at 1-800-LIEBERT to inform them of the damage
7

Installation

Advertisement

Table of Contents
loading

Table of Contents