Appendix - Installation of Remote Termination Panels (RTPs) - Analog Input/Digital Input/Digital Output/Analog
Output
8 Point AC Digital Output
Step
1
ATTENTION: RTP and cables are intended for permanent installation within their own enclosure.
ATTENTION: 8 point AC Output is limited to maximum of 2A per output for any VAC, 6A per RTP for
240VAC, 8A per RTP for 120VAC.
ATTENTION: The RTP combines the 8 isolated outputs into one group of 8.
Mount RTP cable assembly to HC900 Controller (Figure 92).
Remove appropriate key tabs from terminal board to allow mating with the module. See page 75.
Connect desired cable to 8 point AC DO module at controller. Choose from:
900RTC-H010
900RTC-H025
900RTC-H050
Install 8 point AC DO label into the module connector cover.
Connect shield drain wire to the grounding bars at the base of the HC900 rack. All field-wiring
shields must be grounded as described in the shield grounding section (page 70).
2
Mount RTP to DIN rail.
Latch to rail. See page 244.
Connect cable to RTP.
3
Set/verify jumper positions as shown.
Module Removal / Insertion Under Power (RIUP) is supported by turning off Switch SW1 to allow removal of
the module from the rack without causing an arc. See page 73.
ATTENTION: SW1 only disconnects L1, not both sides of the AC powerline.
See page 230 for RTP internal schematic.
228
Remote Terminal High Voltage Cable assembly, 1.0 meters long
Remote Terminal High Voltage Cable assembly, 2.5 meters long
Remote Terminal High Voltage Cable assembly, 5.0 meters long
HC900 Process Controller Installation and User Guide
Action
Jumper open
Jumper closed