IMPORTANT:
continues, proceed with the next step.
Bring the server to base configuration by removing all components that are not required by the
1.
server to complete POST. This process can include removing all:
Expansion boards (on page 48)
o
Processors (on page 36), except the processor installed in socket 1
o
IMPORTANT:
does not function properly.
PPMs ("PPM" on page 41), except the PPM installed in slot 1
o
DIMMs (on page 42), except the first bank
o
Hard drives
("SAS or SATA hard
o
Peripheral devices
o
Install each remaining system component, rebooting between each installation to isolate any failed
2.
components.
Clear the system NVRAM
3.
Replace the system board.
4.
IMPORTANT:
serial number through RBSU
58).
Reboot the server after completing each numbered step. If the error condition
Processor socket 1 and PPM slot 1 must be populated at all times or the server
drives" on page 44)
("System maintenance switch
If replacing the system board or clearing NVRAM, you must re-enter the server
("Re-entering the server serial number and product
(SW3)" on page 76).
ID" on page
Diagnostic tools 67