Chapter 1 Machine Preparation
3. Installation
3-1. How to carry the machine
3-2. How to install the machine
w
q
e
12
Lift up the main body (the frame) to carry the
machine.
(Note) Be sure not to hold and lift the table, equip-
ment, cover, sub-frame, etc. to lift the power
table.
1436S
1. Loosen nut q and adjust the height of
caster w so that the power table be parallel
with the surface of the floor.
2. Descend lever e in order not to move the
main body and fix caster w.
q
Up lever e, then the main body can be movable.
w
e
(Note) If the floor is not solid enough, the machine
may become unstable. Lay something solid
like concrete plates and precede the installa-
tion steps.
1437S
BAS-6150