6.5.2 Connecting the waste water line to a permanent connection

INFORMATION
Prerequisite The waste water line complies with the specifications (see "Unit and
f
e
a
d
b
c
Image: Waste water line to a permanent connection
a Waste water connection
b Waste water line
c Waste water mains
If a siphon is installed in the waste water system, a vacuum breaker must be
installed in the waste water line.
connection data")
1. Install waste water line up to connection to the waste water
system.
2. Secure waste water line with pipe clamps.
3. Fill the siphon of the unit with drinking water.
4. Fill out the Start-up operation report.
Installation instructions
Connecting the unit
d Siphon
e Pipe clamp
f Vacuum breaker