Procedures During Operation - Shindaiwa DG50MKM-P Owner's And Operator's Manual

Diesel engine generator
Table of Contents

Advertisement

① Turn the every circuit breaker to OFF position.
② Turn the Battery Isolator to ON position.
③ Turn the Power switch to ON position.
④ Check MAN mode.
⑤ Press the Start button to start the engine.
< Note >
 If you need to restart, wait at least 30seconds before the retry.
 Be aware that smoke might be generated when the engine is started.
⑥ Let engine idles for approximately for five minutes.
⑦ Adjust the voltage regulator dial to the specified voltage.
⑧ Turn the circuit breakers to ON to start AC power delivery.

9-2. Procedures during Operation

(1) Checks after Startup
 Make sure that the controller is in normal status. (Refer to section "5. Equipment".)
 Check that there is no abnormal vibration or noise.
 Check that the exhaust gas color is normal. When operation is normal, the exhaust gas
should be colorless or slightly bluish.
< Note >
 If abnormal, stop using this generator and request authorized distributor where the
generator was purchased to repair the generator.
Main Circuit Breaker
Power Switch
23
Battery isolator

Advertisement

Table of Contents
loading

This manual is also suitable for:

Dg50mkm-p/anz

Table of Contents