Four processors installed
"AnyBay backplane + AnyBay backplane" on page 45
Two processors installed
Four processors installed
Important:
1. Make sure all the signal cables go through the cable guides.
Figure 25. Cable guide locations
2. Connect the direct NVMe signal cables to the NVMe connectors on the processor and memory
expansion tray.
Figure 26. Connecting NVMe cables to the processor and memory expansion tray
Before starting cable routing for 2.5-inch drives:
1. Remove the fan cage assembly (see
"Remove the fan cage assembly" on page
65).
.
Chapter 2