Figure 126. Power interposer installation
Step 3.
Align the two pairs of nailheads of the system board air baffle to slots, and lower it into the server.
Attention: Air baffle is required for airflow that creates proper cooling. Make sure proper air baffles
for system configuration is installed before the power is turned on.
Figure 127. System board air baffle installation
After installing the system board air baffle, complete the following steps:
1. Reinstall the top cover (see
2. Reconnect the power cords and any cables that you removed.
3. Install the server in the rack.
4. Power on the server and any peripheral devices.
"Install the top cover" on page
146).
.