Installer Manual Riversoft - Commissioning
6.
Commissioning
6.1.
Softener commissioning
6.1.1. Water filling, draining and waterproofness inspection
Once the previous initial programming steps are performed, and that the softener is in place and
hydraulically connected to the main water line (see 4.5.5. Softener installation, page 31), the unit can
be started up.
CAUTION
Do not rotate the camshaft by hand or damage to the unit may occur. Use the controller to
take the camshaft electronically through the cycles.
Follow these steps carefully:
1. With the main water supply closed, open the nearest faucet downstream the unit and the upper
one on the line if not still open from installation step (see 4.5.5. Softener installation, page 31).
2. With the supply water for the system still turned off, position the bypass valve to the "non-
bypass" (normal operation) position for the inlet side, while the outlet stay in bypass position.
Bypass configuration
In
3. Press
on the controller for 3 seconds. This will initiate a manual regeneration.
The controller will activate the motor and turn the camshaft to cycle C1 (Backwash) position. The
controller will display the total regen time remaining in the current cycle.
50 / 90
Out
Manifold configuration
In
Out
Ref. MKT-IM-045 / A - 13.03.2020