5587001-YSG-A-520 | Start-Up & Operation Guide
14. Steam units with humidifier:
a. Steam control valve, Y type strainer, steam trap, and piping are installed .............................
b. Return and discharge air humidity sensors are installed ........................................................
c. Field wiring to the steam control valve is completed ...............................................................
15. Air filters are installed correctly and clean ..................................................................................
16. Shipping bolts have all been removed from the fan assemblies ................................................
17. Install door tieback brackets on the unit base rail. The brackets are used to secure the door in the
open position while servicing. Brackets are shipped loose in the supply fan section of the cabinet .
18. Refrigeration system is checked for gross leaks (presence of oil) .............................................
19. Terminal screws and wiring connections are checked for tightness ...........................................
20. Outside and exhaust air hoods are installed in operating position, if applicable ........................
21. All sensors are properly installed ...............................................................................................
22. The unit has been air balanced ..................................................................................................
23. Site is ready for equipment operation.........................................................................................
24. The unit was modified by a third party manufacturer (such as Fisen) as specified ....................
Observed Product Deficiencies, Concerns, and Notes
I have inspected the installation of the YORK Sun Premier rooftop unit and verified the pre start-up checklist is complete and the
unit is ready to be started up by an approved technician.
Verified by:
With reference to the terms of the above contract, we are requesting the presence of your YORK Authorized Representative at the job site on
____ / ____ / ____ to start the system and instruct operating personnel. Please contact: ___________________________________________
Month
Day
Year
We understand that the services of the YORK Authorized Representative will be furnished in accordance with the contract for a period of time
of not more than _______ consecutive normal working hours, and we agree that a charge of _________ per diem plus travel expenses will be
made to YORK if services are required for longer than ________ consecutive normal hours or if repeated calls are required, through no fault
of YORK.
Customer/Contractor Signature:
Form Completed by:
8
General Inspection
Request for Start-Up
Title:
YORK
IS A REGISTERED TRADEMARK OF JOHNSON CONTROLS
®
© 2020 Johnson Controls | 100 JCI Way, York, Pennsylvania USA 17406-8469 | www.york.com
Subject to change without notice. | Form 773249-YCL-A-520 | Supersedes: 773249-YCL-A-619 | All rights reserved.
The Smart Equipment logo is a trademark of Johnson Controls in the United States and other countries. It is a part
of the Johnson Controls product portfolio.
Date:
Name/Phone
Completed
See Notes