4.3
Using the control panel
Once you have established a connection with the target system and loaded the
project to the target system, a green plug icon appears in front of the drive unit and
other configured components in the project navigator. This indicates that the proj-
ect data in STARTER and the target system is consistent (see Fig. 4-2).
The drive unit is ready to run.
To use the STARTER control panel and start the motor, proceed as follows:
Fig. 4-2
1. Double-click Control panel in the project navigator under Drive_1 > Commis-
sioning (see Fig. 4-2).
The control panel is displayed in STARTER (see Fig. 4-3). You can use the con-
trol panel to control the drive directly from the PC/PG.
Siemens AG, 2004. All rights reserved
SINAMICS S120 Getting Started with the STARTER Commissioning Tool – 04.2004 Edition
Using the STARTER Control Panel (Motor Rotates)
Double-click Control panel in the
project navigator.
Control panel
Green plug icon.