Section 3 • Scheduled Maintenance Procedures
CHECKLIST B PROCEDURES
B-7
Confirm the Proper
Brake Configuration
Genie requires that this procedure be performed
every 250 hours or quarterly, whichever comes
first.
Proper brake configuration is essential to safe
operation and good machine performance.
Hydraulically-released, spring-applied individual
wheel brakes can appear to operate normally when
they are actually not fully operational.
1 Check each drive hub disconnect cap to be
sure it is in the engaged position.
3 - 20
B-8
Inspect the Tires and Wheels
(including lug nut torque)
Genie requires that this procedure be performed
every 250 hours or quarterly, whichever comes
first.
Maintaining the tires and wheels in good
condition is essential to safe operation and good
performance. Tire and/or wheel failure could result
in a machine tip-over. Component damage may
also result if problems are not discovered and
repaired in a timely fashion.
disengaged position
Note: The tires on some machines are foam filled
and do not need air added to them.
1 Check all tire treads and sidewalls for cuts,
engaged position
2 Check each wheel for damage, bends and
3 Check each lug nut for proper torque. Refer to
Models with air-filled tires:
4 Check pressure in each air-filled tire. Add air as
GS-3390 • GS-4390 • GS-5390
Bodily injury hazard. An over-
inflated tire can explode and could
result in death or serious injury.
Tip over hazard. Do not use
temporary flat tire repair products.
cracks, punctures and unusual wear.
cracks.
Section 2, Specifications .
necessary. Refer to Section 2, Specifications .