C. Unit Start-Up

CWP STARTER HAS BEEN PROPERLY INTERLOCKED WITH THE CHILLER

ALL LIQUID VALVES ARE BACKSEATED

ALL DISCHARGE VALVES ARE OPEN

ALL SUCTION VALVES ARE OPEN, IF EQUIPPED

ALL OIL LINE VALVES ARE OPEN

UNIT HAS BEEN LEAK CHECKED
LOCATE, REPAIR, AND REPORT ANY REFRIGERANT LEAKS _____________________________________________
_____________________________________________________________________________________________________
_____________________________________________________________________________________________________
_____________________________________________________________________________________________________
_____________________________________________________________________________________________________

CHECK VOLTAGE IMBALANCE:
AVERAGE VOLTAGE
MAXIMUM DEVIATION
VOLTAGE IMBALANCE

VOLTAGE IMBALANCE IS LESS THAN 2%
DO NOT START CHILLER IF VOLTAGE IMBALANCE IS GREATER THAN 2%. CONTACT LOCAL POWER
COMPANY FOR ASSISTANCE.

ALL INCOMING POWER VOLTAGE IS WITHIN RATED VOLTAGE RANGE
CHECK COMPRESSOR RUNNING CURRENT:
COMPRESSOR
COMP A1,L1
COMP A1,L2
COMP A1,L3
COMP B1,L1
COMP B1,L2
COMP B1,L3
COMP A2,L1
COMP A2,L2
COMP A2,L3
COMP B2,L1
COMP B2,L2
COMP B2,L3
CHECK COOLER WATER LOOP:

INLET PIPING TO COOLER INCLUDES A 20 MESH STRAINER

COOLER FLOW SWITCH SET FOR PROPER MINIMUM FLOW AND COOLER INTERLOCK ENABLED
WATER LOOP DESIGN VOLUME: __________________ GALLONS (LITERS)
CALCULATED VOLUME __________________GALLONS (LITERS)
3 GALLONS/NOMINAL TON (3.32 LITERS/kW) FOR AIR CONDITIONING
6 GALLONS/NOMINAL TON (6.65 LITERS/kW) FOR PROCESS COOLING

PROPER LOOP VOLUME ESTABLISHED

PROPER LOOP CORROSION INHIBITOR INCLUDED ____________GALLONS (LITERS) OF ___________
AB ___________ AC __________ BC _____________
= _________________ (SEE INSTALLATION INSTRUCTIONS)
= _________________ (SEE INSTALLATION INSTRUCTIONS)
= _________________ (SEE INSTALLATION INSTRUCTIONS)
NO LOADERS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
CL-3
ONE LOADER
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
__________AMPS
FULL LOAD