Generator Assembly Installation - Hobart 60CU20 Operation And Maintenance Manual With Illustrated Parts List

60 kva, 3 phase, 115/200 volt, 400 hz. generator set. series 500062
Table of Contents

Advertisement

OM-2226 / Operation and Maintenance Manual
60CU20 / Series 500062 / 400 Hz. Generator Set

3) Generator Assembly Installation

Installation of a generator assembly is essentially a reversal of the procedure for removal of the generator
assembly: the re-mounting of the generator assembly to the frame of the generator set, and the
remounting of the assemblies that were removed to gain access to the generator assembly. To install the
generator assembly, refer to Connection Diagram, and proceed as follows:
a) Remounting the Generator Assembly
(1) Support engine at flywheel housing with wooden blocks, or second hoist if available.
(2) Using the hoist, support the generator assembly and lower it carefully and slowly into position for
attachment to the engine.
(3) While still supporting the generator assembly with the hoist, attach the generator housing to the
engine using the bolts removed earlier. Torque bolts to 30 ft-lb (41 N-m).
(4) Attach the flywheel coupling to the engine using the bolts removed earlier. Torque bolts to 85 ft-
lb (115 N-m).
(5) Mount the generator housing to the frame of the generator set, using the bolts removed earlier.
Torque bolts to 90 ft-lb (122 N-m).
(6) Install the generator wrapper on the generator assembly, using 1/4 - 20 x 1/2 tap-tite screws.
b) Remounting the previously removed assemblies
(1) Remount the remaining pieces of the unit in reverse order of disassembly procedure.
May 2, 2013
Generator Lifting Arrangement
Figure 1
Chapter 3-3
Page 2

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

500062tr-std500062-std500062-dlx500062tr-dlx

Table of Contents