CHAPTER 5
Planning and Preparing the Site
Site Preparation Checklist for ACX1000 and ACX1100 Routers
Table 16: Site Preparation Checklist
Item or Task
Environment
Verify that environmental factors such as
temperature and humidity do not exceed router
tolerances.
Power
Measure the distance between external power
sources and router installation site.
Locate sites for connection of system
grounding.
Calculate the power consumption and
requirements.
Hardware Configuration
Choose the number and types of routers you
want to install.
Rack or Cabinet
Copyright © 2017, Juniper Networks, Inc.
Site Preparation Checklist for ACX1000 and ACX1100 Routers on page 45
General Site Guidelines on page 46
Site Electrical Wiring Guidelines on page 47
The checklist in
Table 16 on page 45
preparing a site for ACX1000 and ACX1100 router installation.
For More Information
"ACX1000 and ACX1100 Router
Environmental Specifications" on
page 57
"ACX1000 and ACX1100 Router
Grounding Specifications" on page 59
"ACX1100 AC Power Specifications"
on page 61
"ACX1000 and ACX1100 DC Power
Specifications" on page 63
"ACX1000 and ACX1100 Universal
Access Router Overview" on page 3
summarizes the tasks you need to perform when
Performed By
Date
45