Lift Control Manifold Service - Toro Reelmaster 7000 Service Manual

Table of Contents

Advertisement

Lift Control Manifold Service

60 in- -lb
(6.8 N- -m)
7
4
20 ft- -lb
(27 N- -m)
6
2
20 ft- -lb
(27 N- -m)
1. Manifold body
2. Relief valve (port RV2)
3. Solenoid valve (port S1)
4. Solenoid coil (5 used)
NOTE: The ports on the manifold are marked for easy
identification of components (e.g. P is the supply con-
nection port and RV1 is the location for the lift relief
valve). See Hydraulic Schematic in Chapter 9 -- Foldout
Drawings to identify the function of the hydraulic lines
and cartridge valves at each port location.
Hydraulic System
8
7
6
Figure 90
5. Solenoid valve (port S2)
6. Solenoid valve (ports S4 and S5)
7. Coil spacer (2 used)
8. Nut
Page 4 - - 120
8
60 in- -lb
(6.8 N- -m)
4
9
10
5
1
9. Solenoid valve (port S3)
10. Relief valve (port RV1)
11. Nut
WARNING
If lift manifold is attached to machine, make sure
that cutting units are fully lowered before loos-
ening hydraulic lines or cartridge valves from lift
manifold. If cutting units are raised as compo-
nents are loosened in manifold, cutting units
may drop unexpectedly.
UP
20 ft- -lb
(27 N- -m)
20 ft- -lb
(27 N- -m)
60 in- -lb
(6.8 N- -m)
11
4
20 ft- -lb
(27 N- -m)
3
Reelmaster 7000