CHAPTER 4
Preparing the Site for the SRX5800
Services Gateway Installation

Site Preparation Checklist for the SRX5800 Services Gateway

Table 21: Site Preparation Checklist
Item or Task
Verify that environmental factors such as
temperature and humidity do not exceed
services gateway tolerances.
Plan rack or cabinet location, including
required space clearances.
Select the type of rack or cabinet.
If a rack is used, secure rack to floor and
building structure.
Acquire cables and connectors.
Locate sites for connection of system
grounding.
Measure distance between external power
sources and services gateway installation site.
Copyright © 2014, Juniper Networks, Inc.
Site Preparation Checklist for the SRX5800 Services Gateway on page 49
SRX5800 Services Gateway Rack Requirements on page 50
SRX5800 Services Gateway Cabinet Requirements on page 53
The checklist in
Table 21 on page 49
preparing a site for services gateway installation.
For More Information ...
"SRX5800 Services Gateway Environmental
Specifications" on page 273
"Clearance Requirements for SRX5800 Services
Gateway Airflow and Hardware Maintenance" on
page 52
"SRX5800 Services Gateway Cabinet Size and
Clearance Requirements" on page
"SRX5800 Services Gateway Rack Size and Strength
Requirements" on page 51
"Connection to Building Structure for the SRX5800
Services Gateway Rack" on page 52
"DC Power Electrical Safety Guidelines and Warnings"
on page 264
summarizes the tasks you need to perform when
54,