Installation Information
Model 315W
Wine Storage
INSTALLATION
Leveling
Note: This model must be leveled prior to installation.
There are four leveler legs on a model 315W, one at
each corner. To level the unit, turn the leveler legs
counterclockwise to raise the unit or clockwise to lower
the unit. (See Figure 2-5)
If the unit is to be built in, with the electrical outlet
behind the installed location, plug unit in and slide back
into position. Check for stability and adjust legs as
needed.
If unit is free standing, move it into place and check for
Figure 2-5. Unit Leveling
stability. Adjust legs as needed. Plug unit into an elec-
trical outlet.
Initial Start-up
When the installation is complete, be sure to remove all
tape and packing materials before initial start-up.
Locate the temperature control knob on the bottom front
of unit. Rotate knob clockwise to an operating position.
(See Figure 2-6)
You should immediately hear a humming noise and feel
air blowing in and out of the vents near the knob. (See
Figure 2-7) After 10 minutes open the door and feel the
back panel inside the cabinet. It should feel cold to the
touch.
Figure 2-6. Temperature Control
To switch refrigeration off, rotate the temperature con-
trol knob fully counterclockwise. The light will still be
operational.
Figure 2-7. Air Flow
2-4
#3758664 - First Edition - July, 2005