STEP 1
Locate vent opening on the wall. It may be necessary to
first position the fireplace and measure to obtain hole
location. Depending on whether the wall is combustible
or noncombustible, cut opening to size. (Fig. 19)
For combustible walls first frame in opening.
Combustible Walls: Cut a 16¹⁄₄"H x 16¹⁄₄" W (413mm x
413mm) hole through the exterior wall and frame as
shown.
Noncombustible Walls: Hole opening must be 11¹⁄₄"
(286mm) in diameter.
Vent Opening for Combustible Wall
16¹⁄₄"
(413mm)
16¹⁄₄"
(413mm)
Fireplace Hearth
Vent Opening for Noncombustible Wall
11¹⁄₄"
(286mm)
Fig. 19 Locate vent opening on wall.
STEP 2
Measure wall thickness and cut zero clearance sleeve
parts to proper length (MAXIMUM 12"/305 mm).
Assemble sleeve using #8 sheet metal screws (sup-
plied). (Fig. 20) Install firestop assembly. (Fig. 30)
Zero clearance sleeve is only required for
combustible walls.
Adjustable Zero
Clearance Sleeve
#8 Screws (2)
Fig. 20 Adjustable zero clearance sleeve.
14
STEP 3
Slide the zero clearance sleeve through the wall and
install the firestop on the inside surface of the wall.
Secure with four (4) #8 sheet metal screws.
STEP 4
Place fireplace into position. (Fig. 21) Measure the
vertical height (X) required from the base of the flue
collars to the center of the wall opening. NOTE: If using
the SK8DVSK Kit, the vertical section of pipe is tel-
escopic and could provide adjustment from 24" up to
40" (610mm to 1016mm).
Framing
Detail
VO584-100
Fig. 21 Vertical height requirement.
STEP 5
Tape the inner and outer flue collars of the fireplace
using UL approved metal adhesive tape to ensure the
joints are sealed. Attach an appropriate length of vent
pipe to the fireplace. Follow with the installation of the
inner and outer elbow, tape elbow joints and secure
joints as described on Page 11.
STEP 6
Measure the horizontal length requirement including a
2" (50mm) overlap, ie from the elbow to the outside wall
face plus 2" (50mm) (or the distance required if install-
Max. Length
12" (305mm)
ing a second 90° elbow). (Fig. 22)
#8 Screws (2)
STEP 7
Use appropriate length of pipe sections and install the
horizontal vent sections. You may need to cut 1' wall
section to size to be flush with the outside wall. The
sections which go through the wall are packaged with
ZCS101a
the starter kit, and can be cut to suit if necessary. (Fig.
23)
Firestop
X
Always install horizontal venting on a
level plane.
Zero
Clearance
Sleeve
FP1456
20007172

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents