• The inverter carries out four test sequences, all of which are displayed on the screen.
• After the test is finalized, each test result must be confirmed by entering Next.
• After entering Finish on the last result, the screen displays the Inverter Commands menu.
• The test results can be found in Commands>Inverter Commands>Results Self Test.
Refer to User Guide for more detailed information about the Italian Self Test