Installing patch panels

Patch panels are arrays of RJ45 jacks and associated B25A cabling to accommodate 2-wire,
24-port DCP/analog port boards and 8-port analog trunk boards. They are mounted either
below or above the media gateway stack. They cannot be mounted in between media
gateways.
Note:
The patch panels do not have to be mounted in the same rack as the media
Note:
gateways. They can be mounted in phone closets as appropriate.
See
Figure 44: Typical RMC patch panel installation
procedure.
To install patch panels:
1. Using the supplied mounting screws, mount the patch panels on the rack below media
gateway A or above the topmost media gateway.
2. Attach B25A cables to the patch panels and the circuit pack amphenol connectors.
Note:
Connect 24-port DCP/analog circuit packs to the 24 port patch panels.
Note:
Note:
Connect 8 port analog trunk, "combo," or DID trunk circuit packs to either of the
Note:
first two banks on the 8 port patch panel. If an TN2185B ISDN-BRI S/T-TE
Interface (4-wire, 8 ports) circuit pack is present, connect it to the third bank on
the 8 port patch panel.

Cross-connecting the media gateway to the patch panels

Cross-connect the port circuit packs to the G650 Media Gateway patch panels (or other
standard 110A cross-connect equipment). See
patch panel connections
on page 111.
on page 110 while performing this
Figure 45: Example cross-connect field
Issue 2 January 2005