➢ ➢ ➢ ➢ To test the system's inverting and charging functions
1. Apply DC to both inverter•chargers by closing the battery disconnect(s).
2. Set the INVERTER switch on one display to ENABLE.
3. Enable the inverter on the second display.
4. Place a 120V load on the master inverter (e.g. plug a light into an outlet
5. To test Charge mode, apply AC to both inverter•chargers by closing the
6. Check a transfer by opening the AC source breaker. The inverter•chargers
If any part of this procedure fails, determine the cause before using the
inverter•chargers. Consult the
as necessary.
92
U
'
M
SER
S
ANUAL
S
S
YSTEM
TARTUP
Remove AC by opening the AC input source breaker. On both
inverter•chargers, set the ON/OFF/REM switch to On.
The INVERTER STANDBY LED on that display should light.
The INVERTING LED on both displays should light.
that it is powering) and make sure it works. Place a second 120V load on
the output of the slave inverter and verify that both loads work. Place a
240V load on the 240V circuit formed by the two series inverters and
verify that it works correctly.
AC input source breaker.
After a few seconds both units should transfer: the INVERTING LEDs
will go dark and the AC IN LEDs will light. Enable the charger on both
displays: the CHARGING LED on both displays should light and battery
current should be registered. Any AC loads powered by the inverter will
also work from shorepower at this time.
should transfer to Invert mode immediately: the transfer relays will make
a clicking sound and the INVERTING LED on both displays will come
on. Loads will continue to operate uninterrupted.
T
EST
"Troubleshooting"
section starting on
page 71