HP rp7420 Service Manual page 65

Hp 9000 rp7420 server - user service guide, fifth edition
Hide thumbs Also See for rp7420:
Table of Contents

Advertisement

Table 4-2 Factory-Integrated Installation Checklist (continued)
PROCEDURE
Inspect shipping containers for
damage
Unpack SPU cabinet
Allow proper clearance
Cut polystrap bands
Remove cardboard top cap
Remove corrugated wrap
from the pallet
Remove four bolts holding
down the ramps and
remove the ramps
Remove antistatic bag
Check for damage (exterior
and interior)
Position ramps
Roll cabinet off ramp
Unpack the peripheral cabinet
(if ordered)
Unpack other equipment
Remove and dispose of
packaging material
Move cabinet(s) and equipment
to computer room
Move cabinets into final position
Position cabinets next to
each other (approximately
1/2 inch)
Adjust leveling feet
Install anti-tip plates
Inspect cables for proper
installation
Set up CE tool and connect to
Remote RS-232 port on MP
Apply power to cabinet
(housekeeping)
Check power to BPSs
Log in to the MP
Set LAN IP address on the MP
Connect customer console
Set up network on customer
console
Verify LAN connection
IN-PROCESS
COMPLETED
Using the Checklist
65

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

9000 rp7420

Table of Contents