Step 5: Powering Up And Powering Down The Components In The Rack; Power Up Sequence; Power Down Considerations - HP D5970A - NetServer - LCII Reference Manual

Rack cabling reference guide
Hide thumbs Also See for D5970A - NetServer - LCII:
Table of Contents

Advertisement

Chapter 3
and adjust as necessary. Repeat until the Cable Management Arm extends
and retracts smoothly.
6. Secure the server to the front of the rack with screws and rack nuts and
replace the bezel. See the HP NetServer LC 2000/2000r Installation Guide
for details.
Step 5: Powering Up and Powering Down the
Components in the Rack
Follow the Power Up Sequence to minimize inrush currents and prevent breakers
from tripping.

Power Up Sequence

1. Power on peripherals one at a time, beginning with the tape back-up unit,
continuing with the mass storage units, monitor, and the rest.
2. If an HP Console Switch is present, it must be on before the server is
powered on. Otherwise the server will not detect all the required
components and will likely report an error.
3. Lastly, power on one server at a time, waiting for fan units in one to spin
up before powering on the next (if more than one is present in the rack).

Power Down Considerations

To power off the equipment, ensure that network users are properly warned. No
specific order is necessary when powering off rack-optimized servers and
associated components. However, to do so in an orderly way, you should bring
down the operating system, then power off peripherals, then turn off servers.
WARNING
The HP NetServer LC 2000r is connected to standby power
even when power is turned off. Do not open the system for
maintenance except if you have removed the power cord.
50
Procedure for Connecting and Routing Cables to the LC 2000r