Mandik SEDM-L Installation, Operation, Maintenance And Service Manual

Multi compartment smoke control damper
Hide thumbs Also See for SEDM-L:

Advertisement

Quick Links

TPM 146/20
Version 2024-04-29
SEDM-L
Multi compartment smoke control damper
Technical Documentation
Installation, Commissioning, Operation, Maintenance and Service Manual
www.mandik.com
MANDÍK, a. s. • Dobříšská 550 • 267 24 Hostomice • Czech Republic • Tel.: +420 311 706 742 • E-Mail: mandik@mandik.cz

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the SEDM-L and is the answer not in the manual?

Questions and answers

Summary of Contents for Mandik SEDM-L

  • Page 1 Version 2024-04-29 SEDM-L Multi compartment smoke control damper Technical Documentation Installation, Commissioning, Operation, Maintenance and Service Manual www.mandik.com MANDÍK, a. s. • Dobříšská 550 • 267 24 Hostomice • Czech Republic • Tel.: +420 311 706 742 • E-Mail: mandik@mandik.cz...
  • Page 2: Table Of Contents

    VIII. TRANSPORTATION, STORAGE AND WARRANTY........................62 Logistic terms..................................62 Warranty....................................62 IX. ASSEMBLY, ATTENDANCE AND MAINTENANCE........................62 Electrical connection of the actuator in protection box....................63 Entry into service and revisions............................64 X. ORDERING INFORMATION...............................65 Ordering key..................................65 Data label....................................65 Page 2 Multi compartment smoke control damper - SEDM-L Version 2024-04-29...
  • Page 3: General

    TPM 146/20 I. GENERAL Description Smoke control dampers - SEDM-L are designed into an inlet according to EN 1366-8) or they can be installed in or on the or extract smoke ventilation system. The dampers are construction of the fire compartment.
  • Page 4 The dampers used to supply air in the affected fire section ■ ■ are installed at the ground. If necessary, in the event of a fire, the SEDM-L dampers in ■ the affected fire section will open completely so that the The dampers are controlled from the central control ■...
  • Page 5: Design

    1 Damper housing 6 Blade stop 2 Blades 7 Actuator housing 3 Silicone blade seal 8 Actuator housing cover 4 Internal silicone seal 9 Actuator 5 Fire-fighting foam tape Version 2024-04-29 Multi compartment smoke control damper - SEDM-L Page 5...
  • Page 6 (BEN 24-ST) with plug Cable 1 m, 6 x 0,75 mm Cable 1 m, 6 x 0,75 mm - auxiliary switch connectors * Only available for 24V and selected damper sizes Page 6 Multi compartment smoke control damper - SEDM-L Version 2024-04-29...
  • Page 7 (BEE 24-ST) with plug Cable 1 m, 6 x 0,75 mm Cable 1 m, 6 x 0,75 mm - auxiliary switch connectors * Only available for 24V and selected damper sizes Version 2024-04-29 Multi compartment smoke control damper - SEDM-L Page 7...
  • Page 8 Storage temperature -40°C … +80°C Cable 1 m, 3 x 0,75 mm Connection - drive Cable 1 m, 6 x 0,75 mm - auxiliary switch (BE 24-ST) with plug connectors Page 8 Multi compartment smoke control damper - SEDM-L Version 2024-04-29...
  • Page 9: Design With The Communication And Supply Device

    Blade stop 2 Blades Actuator housing 3 Silicone blade seal Actuator housing cover 4 Internal silicone seal Actuator 5 Fire-fighting foam tape 10 Communication and power supply device BKNE 230-24 Version 2024-04-29 Multi compartment smoke control damper - SEDM-L Page 9...
  • Page 10 -40°C … +80°C Connection - net cable 0,9 m with EURO plug type 26 - motor 6-pole connector, 3-pole connector - terminal board screw terminals for cable 2x1,5 mm² Page 10 Multi compartment smoke control damper - SEDM-L Version 2024-04-29...
  • Page 11: Communication And Control Device Bkse 24-6

    5,5 VA 18 VA (Imax 6.4 A @ 2.5 ms) Protection class Degree of protection IP 20 Ambient operation temperature 0°C … +50°C Connection terminal 2 x 1,5 mm Version 2024-04-29 Multi compartment smoke control damper - SEDM-L Page 11...
  • Page 12: Iii.dimensions

    III.DIMENSIONS SEDM-L without flange and cover grille The blade spacing is always 200mm ■ SEDM-L with flange and cover grille over blades * External dimension of the grille The blade spacing is always 200mm ■ For a detail of the cover grille filling, →...
  • Page 13 TPM 146/20 SEDM-L with flange and cover grille over damper * External dimension of the grille ■ The blade spacing is always 200mm For a detail of the cover grille filling, → see page 14 ■ Flange (2 types) Flange over blades...
  • Page 14 The grilles type KMM (TPM 002/96) can be used to close smoke control dampers. ■ Maximum size KMM can we supply is 2400x2400mm. ■ Free area value for KMM is 78%. ■ Page 14 Multi compartment smoke control damper - SEDM-L Version 2024-04-29...
  • Page 15: Technical Parameters

    0,6009 104,3 1050 0,6314 106,7 1100 0,6619 109,1 1150 0,6924 111,5 1200 0,7229 113,9 * In case of BKNE design it is necessary to add the weight 0,68 kg. Version 2024-04-29 Multi compartment smoke control damper - SEDM-L Page 15...
  • Page 16 (40 N.m) 1050 1,1282 160,2 1100 1,1827 163,7 1150 1,2372 167,1 1200 1,2917 170,6 * In case of BKNE design it is necessary to add the weight 0,68 kg. Page 16 Multi compartment smoke control damper - SEDM-L Version 2024-04-29...
  • Page 17 213,4 10,7 1100 1,7035 217,9 1150 1,7820 222,4 11,3 1200 1,8605 226,9 10,1 11,6 * In case of BKNE design it is necessary to add the weight 0,68 kg. Version 2024-04-29 Multi compartment smoke control damper - SEDM-L Page 17...
  • Page 18: Installation

    200 mm between dampers, according to EN 1366-10 ■ ■ minimum distance 75 mm between damper and construction (wall/ceiling), according to EN 1366-10 ≥ 75 ≥ 200 Page 18 Multi compartment smoke control damper - SEDM-L Version 2024-04-29...
  • Page 19 TPM 146/20 Recommended construction openings Mortar or gypsum Ablative Coated Batt system x = 200 mm…400 mm x = 50 mm Version 2024-04-29 Multi compartment smoke control damper - SEDM-L Page 19...
  • Page 20: Transport Of The Damper To The Installation Place And The Installation Procedure

    2. Place handling inserts between the top blade and the damper housing. Handling inserts Damper housing Blade stop Handling inserts 2pc (included in package of larger dimensions SEDM-L) Blade Board - thickness min. 25mm (not included) Forks 3. Drive the forklift under the highest blade. It’s necessary to put a board between the blade and the fork along the blade’s entire length so that the blade is not damaged when the damper is raised.
  • Page 21 TPM 146/20 4. Place the damper in the installation hole. 5. After installing the damper and possibly hardening the plaster/mortar, remove the transport struts and corners. Version 2024-04-29 Multi compartment smoke control damper - SEDM-L Page 21...
  • Page 22 Flange over blades Detail X Detail Y Flange edge Damper edge The inner edge of the damper aligns with the inner edge of the flange Detail Y Detail X SEDM-L Flange Page 22 Multi compartment smoke control damper - SEDM-L Version 2024-04-29...
  • Page 23 8. Ways of placing the grille on the damper with a flange (2 types) Grille over blades Grille over damper For a detail of the cover grille filling, → see page 14 ■ Version 2024-04-29 Multi compartment smoke control damper - SEDM-L Page 23...
  • Page 24 Rivet nuts (mounted on the flange from the factor) 10. Mounting the handrail on the damper SEDM-L Pre-drilled holes Handrail (part of SEDM-L) Screw UNI 5x50 mm (part of SEDM-L) Page 24 Multi compartment smoke control damper - SEDM-L Version 2024-04-29...
  • Page 25: Statement Of Installations

    S1000C HOT 400/30MAmulti 46-47 ↔ extraction ducts with insulation ducts tested according to EN 1366-8 or EN 1366-9 Application as a wall ** Application as a shaft wall Version 2024-04-29 Multi compartment smoke control damper - SEDM-L Page 25...
  • Page 26: Installation In Solid Wall Construction

    Examples of anchors to the fire dividing ■ construction → see pages 48 to 50 SEDM-L Solid wall construction Mortar or gypsum Flange Grille Page 26 Multi compartment smoke control damper - SEDM-L Version 2024-04-29...
  • Page 27 Fire-resistant mastic - (HILTI CFS-S ACR...) fill the gap from both sides of the fire separation construction and around the perimeter of penetration and damper casing. Version 2024-04-29 Multi compartment smoke control damper - SEDM-L Page 27...
  • Page 28: Installation In Gypsum Wall Construction

    Fire-resistant mastic - (HILTI CFS-S ACR...) fill the gap from both sides of the fire separation construction and around the perimeter of penetration and damper casing. Page 28 Multi compartment smoke control damper - SEDM-L Version 2024-04-29...
  • Page 29: Installation In Battery

    Seal all joints (Overplating strips, Spacing strips ■ with SEDM-L damper) with Promat glue K84. Examples of anchors to the fire dividing con- ■ struction → see pages 48 to 50 * RESPECT JOINT POSITION ! Bolts and nuts shall not prevent free rotation on the blades.
  • Page 30 Seal all joints (Overplating strips, Spacing strips ■ with SEDM-L damper) with Promat glue K84. Examples of anchors to the fire dividing con- ■ struction →...
  • Page 31 Seal all joints (Overplating strips, Spacing strips ■ with SEDM-L damper) with Promat glue K84. Examples of anchors to the fire dividing con- ■ struction →...
  • Page 32 Seal all joints (Overplating strips, Spacing strips ■ with SEDM-L damper) with Promat glue K84. Examples of anchors to the fire dividing con- ■ struction → see pages 48 to 50...
  • Page 33 Seal all joints (Overplating strips, Spacing strips ■ with SEDM-L damper) with Promat glue K84. Examples of anchors to the fire dividing con- ■ struction →...
  • Page 34 200...400 Seal all joints (Overplating strips, Spacing strips ■ with SEDM-L damper) with Promat glue K84. Examples of anchors to the fire dividing con- ■ struction → see pages 48 to 50...
  • Page 35 ≥ 100 Seal all joints (Overplating strips, Spacing strips ■ with SEDM-L damper) with Promat glue K84. Examples of anchors to the fire dividing con- ■ struction → see pages 48 to 50 * When installing a flange, overplating strip is not installed.
  • Page 36 ≥ 100 Seal all joints (Overplating strips, Spacing strips ■ with SEDM-L damper) with Promat glue K84. ■ Examples of anchors to the fire dividing con- struction → see pages 48 to 50 * When installing a flange, overplating strip is not installed.
  • Page 37 ≥ 100 Seal all joints (Overplating strips, Spacing strips ■ with SEDM-L damper) with Promat glue K84. Examples of anchors to the fire dividing con- ■ struction → see pages 48 to 50 * When installing a flange, overplating strip is not installed.
  • Page 38 Seal all joints (Overplating strips, Spacing strips ■ ≥ 100 with SEDM-L damper) with Promat glue K84. Examples of anchors to the fire dividing con- ■ struction → see pages 48 to 50 * When installing a flange, overplating strip is not installed.
  • Page 39 Seal all joints (Overplating strips, Spacing strips ■ with SEDM-L damper) with Promat glue K84. Examples of anchors to the fire dividing con- ■ struction →...
  • Page 40 Seal all joints (Overplating strips, Spacing strips ■ with SEDM-L damper) with Promat glue K84. Examples of anchors to the fire dividing con- ■ struction →...
  • Page 41 ■ Seal all joints (Overplating strips, Spacing strips with SEDM-L damper) with Promat glue K84. Examples of anchors to the fire dividing con- ■ struction → see pages 48 to 50 ≥...
  • Page 42 Seal all joints (Overplating strips, Spacing strips ■ with SEDM-L damper) with Promat glue K84. Examples of anchors to the fire dividing con- ■ struction →...
  • Page 43 4 dampers - gypsum wall - ablative coated batt EI 120 S Seal all joints (Overplating strips, Spacing strips ■ with SEDM-L damper) with Promat glue K84. Examples of anchors to the fire dividing con- ■ struction → see pages 48 to 50 200...400...
  • Page 44: Installation In Shaft Wall British Gypsum

    SEDM-L Mortar or gypsum Plasterboard EN 520 - Type F min. 3x15 mm Plasterboard EN 520 - Type F min. 1x19 mm Plasteboard profile Page 44 Multi compartment smoke control damper - SEDM-L Version 2024-04-29...
  • Page 45: Installation In Solid Ceiling Construction

    Installation in solid ceiling construction In solid ceiling construction - mortar or gypsum EI 120 S - application as a shaft SEDM-L Solid ceiling construction Mortar or gypsum Flange Grille Version 2024-04-29 Multi compartment smoke control damper - SEDM-L Page 45...
  • Page 46: Installation Damper Into/Onto Smoke Extraction Ducts

    Smoke extraction duct (according to duct manufacturer) Surface protection material (according to duct manufacturer) Steel instulation pin (according to duct manufacturer) (continued on next page) Smoke extraction damper and duct supports (according to duct manufacturer) Page 46 Multi compartment smoke control damper - SEDM-L Version 2024-04-29...
  • Page 47 11 Intumescent acrylic Sealant - arround the duct circumference (type according to duct manufacturer instructions)* 12 Insulation connection to the damper body - washer M5 (DIN 125A), screw 5xL mm (screw lenght = insullation thickness + 20 mm) Version 2024-04-29 Multi compartment smoke control damper - SEDM-L Page 47...
  • Page 48: Suspension Systems

    TPM 146/20 V. SUSPENSION SYSTEMS Fixing SEDM-L to the solid wall construction - Ablative Coated Batt system View A N => number of blades FOR: A < 500 => 1 anchor A ≥ 500 => 2 anchor FOR: B = 430 and 630 => 1 anchor B = 830, 1030, 1230 =>...
  • Page 49 TPM 146/20 Fixing SEDM-L to the gypsum wall construction - Ablative Coated Batt system View A View A - grid from "C" profile The method of mounting must meet the minimum requirements ■ for attachment in accordance with national regulations.
  • Page 50 Fixing element/steel bracket for connecting damper to the wall Fixing element/steel bracket for connecting damper to the wall (optional accessories MANDIK, a.s. or sheet metal min. thickness 2 mm and min. width 60 mm) Installation hols M8 bolt assemply (bolt M8x55 mm, 2 pcs large washer M8, nut M8)
  • Page 51: Example Of Duct Connection

    Smoke extraction duct - tested acc.to EN 1366-8 or EN 1366-9 Fire separating constructions Overplating strip - min. th. 30 mm, the same material as a duct. Surface protection material (type according to duct manufacturer instructions) Penetration seal Version 2024-04-29 Multi compartment smoke control damper - SEDM-L Page 51...
  • Page 52: Technical Data

    → see pages 53 to 56 Determination of pressure loss by using diagram ρ = 1,2 kg/m air flow speed w [m/s] Page 52 Multi compartment smoke control damper - SEDM-L Version 2024-04-29...
  • Page 53 0,579 0,516 0,487 0,471 0,460 0,453 0,447 0,443 0,440 1150 0,578 0,515 0,487 0,470 0,460 0,452 0,447 0,443 0,439 1200 0,577 0,515 0,486 0,470 0,459 0,452 0,446 0,442 0,439 Version 2024-04-29 Multi compartment smoke control damper - SEDM-L Page 53...
  • Page 54 2,199 2,080 2,026 1,995 1,975 1,960 1,950 1,942 1,936 1150 2,198 2,079 2,024 1,993 1,973 1,959 1,949 1,941 1,935 1200 2,197 2,078 2,023 1,993 1,972 1,958 1,948 1,940 1,934 Page 54 Multi compartment smoke control damper - SEDM-L Version 2024-04-29...
  • Page 55 2,112 2,003 1,953 1,924 1,905 1,893 1,883 1,876 1,870 1150 2,111 2,001 1,951 1,923 1,905 1,892 1,882 1,875 1,869 1200 2,110 2,000 1,951 1,922 1,904 1,891 1,881 1,874 1,868 Version 2024-04-29 Multi compartment smoke control damper - SEDM-L Page 55...
  • Page 56 4,545 4,269 4,143 4,072 4,025 3,993 3,969 3,950 3,936 1150 4,542 4,266 4,141 4,069 4,023 3,990 3,966 3,948 3,933 1200 4,540 4,264 4,139 4,067 4,021 3,988 3,964 3,946 3,931 Page 56 Multi compartment smoke control damper - SEDM-L Version 2024-04-29...
  • Page 57: Noise Data - Level Of Acoustic Output Corrected With Filter A

    1430 1630 1830 2030 1000 1050 1100 1150 1200 Air velocity 3 m/s Level of acoustic output [dB] 1030 1230 1430 1630 1830 2030 1000 1050 1100 1150 1200 Version 2024-04-29 Multi compartment smoke control damper - SEDM-L Page 57...
  • Page 58 1430 1630 1830 2030 1000 1050 1100 1150 1200 Air velocity 5 m/s Level of acoustic output [dB] 1030 1230 1430 1630 1830 2030 1000 1050 1100 1150 1200 Page 58 Multi compartment smoke control damper - SEDM-L Version 2024-04-29...
  • Page 59 1430 1630 1830 2030 1000 1050 1100 1150 1200 Air velocity 8 m/s Level of acoustic output [dB] 1030 1230 1430 1630 1830 2030 1000 1050 1100 1150 1200 Version 2024-04-29 Multi compartment smoke control damper - SEDM-L Page 59...
  • Page 60 1430 1630 1830 2030 1000 1050 1100 1150 1200 Air velocity 12 m/s Level of acoustic output [dB] 1030 1230 1430 1630 1830 2030 1000 1050 1100 1150 1200 Page 60 Multi compartment smoke control damper - SEDM-L Version 2024-04-29...
  • Page 61: Material, Finishing

    The blade in the variants for chemical environments (Class A4) is always treated with a coating of chemically resistant Promat SR. Any other requirements for the design shall be considered atypical and shall be addressed on an individual basis. Version 2024-04-29 Multi compartment smoke control damper - SEDM-L Page 61...
  • Page 62: Transportation, Storage And Warranty

    The warranty for fire dampers SEDM-L, provided by the ■ are mechanically damaged during handling. manufacturer, is completely void if actuating, closing and...
  • Page 63: Electrical Connection Of The Actuator In Protection Box

    Dimensions also apply to the top and bottom Drilling areas for routing the connection cable to the actuator example drilled holes Example of position of holes in the wall of the box, without pre-manufactured slot Version 2024-04-29 Multi compartment smoke control damper - SEDM-L Page 63...
  • Page 64: Entry Into Service And Revisions

    Dampers blades should open and close correctly and op- eration should be visually inspected and documented prior to handover. Actuator housing cover detail Page 64 Multi compartment smoke control damper - SEDM-L Version 2024-04-29...
  • Page 65: Ordering Information

    M2 - flange and grille over damper** design size AxB EXAMPLE: SEDM-L 1200x2030 .44/M2/– 1200x2030-damper size, .44-damper design, M2-flange and grille over damper, –without flange and grile on right side Dampers design Additional digit with actuating mechanism BEN, BEE, BE for 230V...