Commissioning

10.1

Post-mounting and post-connection check

Before commissioning the device:
Make sure that the post-installation and post-connection checks have been performed
successfully.
• Checklist for "Post-mounting" check→  25
• Checklist for "Post-connection check" →  30
10.2

Switching on the measuring device

The function check has been completed successfully.
Switch on the supply voltage.
 The measuring device runs through internal test functions.
The device is operational and operation commences.
If the device does not start up successfully, depending on the cause, a diagnostic
message is displayed in the system asset management tool "FieldCare" .
10.3

Connecting via FieldCare

• For connecting FieldCare →  31
• For connecting via FieldCare →  32
• For user interface of FieldCare →  33
10.4

Configuring the measuring instrument

The device-specific parameters are configured via the "Commissioning wizard".
For detailed information on the "Commissioning wizard": Separate "Description of
Device Parameters "(GP) document