4.3 Commission multiple inverters – Auto ID Function
The Auto ID function can set all inverter IDs at once by DSS
or DeltaSolar APP.
- DSS
Connect the inverter through RS-485 with computer.
- APP
Connect the inverter through DC1 with mobile device.
(please refer to chapter 4.4 for operation manual.)

4.3.1 Commission Setting (DSS)

① Select the corresponding model
② Click "RS485"
③ Select communication port (automatic detection by the system).
④ Click
Figure 4-5: DSS Commission setting