CONTENTS INTRODUCTION ................................3 1. DESCRIPTION AND OPERATION ........................5 1.1 General Information and Purpose ......................... 5 1.2 Specifications ................................ 6 1.3 Configuration and Scope of Delivery........................6 1.4 Design and operation ............................9 1.5 Instrumentation, tools and accessories ........................ 10 1.6 Description and operation of controllers as an integral component of the turnstile ..........
INTRODUCTION This Operation Manual (hereinafter referred to as OM) covers the "SWEEPER-HG" type waist-high turnstile (hereinafter referred to as the "turnstile"). The Operation Manual contains information about design, specifications, installation for proper operation and maintenance of the turnstile. This Operation Manual is prepared in compliance with the specification requirements ТU U 28.9- 32421280- 005:2018.
Page 4
WARNINGS TO THE CUSTOMER ON SAFE OPERATION OF THE TURNSTILE These warnings are designed for ensuring of safety during operation of the turnstile to prevent violation of safety characteristics by improper installation or operation. These warnings are aimed at drawing attention of the customer to safety problems.
1. DESCRIPTION AND OPERATION 1.1 General Information and Purpose 1.1.1 Purpose: The motorized turnstile is designed for pedestrian movement control at access points of industrial enterprises, banks, stadiums, administrative facilities etc. controlled by access control system (from proximity card readers) or manually (from manual control panel).
1.1.3 The turnstile component identification codes are specified in Table 2. Table 2 Max. weight, Description of the turnstile Dimensions, mm, Order code Н В component Т3.КСD.PD Left-hand/right-hand cabinet Т3.КСD.SD Т3.КСD.KD 1800/1500 1435 Т3.КСD.PD.X Additional cabinet Т3.КСD.SD.X Т3.КСD.KD.X 1.1.4 The operation condition parameters according to GOST 15150-69 are specified in Table 3 Table 3 Operation conditions Parameter value for climatic modification NF4...
Page 7
1.3.2 Design of the single turnstile of "SWEEPER-HG-1" type The single turnstile consists of two single side cabinets (Slave and Master). The single leaf cabinet housing includes: frame; swing-type side pieces with locks; top, side and bottom linings; ...
Page 8
1.3.6 Design and general appearance of the turnstile 1.3.6.1 The cabinet body is a frame 12 on which stainless steel side, top and bottom linings 1, 2, 6, 11, 8mm- tempered glass partition 5 are installed. Decorative lid 10 is fixed on frame from the top (lining material is defined by order).
1.5 Instrumentation, tools and accessories Dedicated tools are not required for installation of the turnstile (multi-purpose measurement instrumentation and installation tools are sufficient). 1.6 Description and operation of controllers as an integral component of the turnstile 1.6.1 Controller AUIA.206.21.20.00 1.6.1.1 Controller AUIA.206.21.20.00 is shown in Figure 5. 1.6.1.2 Description of operation The controller provides algorithm of operation of the whole turnstile.
Page 11
1 - ON - when command is issued, the turnstile will open for 5 seconds; - OFF - when command is issued, the turnstile will open for the time set in ACS; 2 - ON - Outputs OUT1-5 will be NC; - OFF - Outputs OUT1-5 will be O;...
Page 12
ALARM The turnstile goes to this mode from any above mentioned mode in case of unauthorized access attempts. Meanwhile red LED is frequently blinking (4 times per second), siren alarm is generated on the turnstile and control panel and output "OUT5" is activated on the controller card. If the turnstile was opened, then swing leaves would be closed if there were no obstacles in the closing area.
Page 13
Continued Table 5 ХТ1/1 1) type of output – open collector; peak voltage on privacy key 60V; 3) peak current of Output for connection of public key 250mA; audible alarm. The output is 4) resistance of active in case of unauthorized public key access (0,48÷...
Page 14
Table 6 Connector Signal parameters Direction Designation Purpose /Contact No and description « TO BE OPENED A» X1/1 ENTRY « TO BE OPENED В» 1) logical «0» (0 1,7) V; X1/2 ENTRY « LOCKING» 2) logical «1» (3,7 5) V; X1/3 ENTRY To be connected to microswitch...
2 INTENDED USE 2.1 Operation limitations 2.1.1 The turnstile must be used in the environment specified in p. 1.1.5 of this document subject to the specifications listed in section 1.2. IT IS FORBIDDEN: 1) TO MISUSE THE TURNSTILE (See section 1 "DESCRIPTION AND OPERATION"); 2) TO USE THE TURNSTILE UNEARTHED;...
Page 16
2.2.5 SWEEPER-HG type turnstile layout options Fig. 8 – SWEEPER-HG type turnstile layout options WARNING: The damages occurred during the turnstile transportation are not covered by the manufacturer's warranty liabilities. 2.2.6 Installation procedure 2.2.6.1 The turnstile installation procedure is as follows: 1) The package integrity to be checked prior to unpacking.
Page 17
2.2.6.2 Turnstile dismantling and relocation: To remove the turnstile from the pallet (see Fig. 9) you must open the side pieces. The side pieces are designed as a hinged door and are closed by locks. - Locks to be opened by key and door to be turned from both sides of cabinet (View А);...
Page 18
2.2.6.4 The following cables to be run to the turnstile installation site: Power supply cable 220 V ~; Control panel connection cable; Access Control System connection cables, if available; Cables between cabinets; Cables to be run in corrugated or metal pipes. SWEEPER-HG-1 SWEEPER-HG-1 Slave...
Page 19
Option 1 Option 2 Fig.12 – Options of cable connection between cabinets Master and Slave The length of cable free ends to be at least 1 m to provide their entry, termination and connection to the relevant terminals in the turnstile post. The cable outlet location to be aligned with the hole on the turnstile mounting plate.
Page 20
2.2.6.5 Installation in design position To access the fixation holes and terminal blocks it is required on both sides of cabinets: 1. - Locks to be opened by key and door to be turned (See Fig. 13); 2. - Bottom linings to removed by unscrewing screws M5-6g x14;...
Page 21
2.2.6.6 Turnstile connection: a) Power supply cable ~220 V to be connected (Fig. 14): - Phase L to be connected to the circuit breaker; - Neutral (N) to be connected to terminal ~220V (N); - Earth (РЕ) to be connected to earthing terminal (РЕ).
2.3 Preparation for use 2.3.1 Commissioning guidelines Prior to the turnstile energization: 1) make sure of proper connection and good condition of all connecting cables; 2) clear the turnstile’s leaf swing area from foreign particles. When mains cable of power supply unit is connected to the network the turnstile’s operating mechanism is energized: leaves are locked from rotation in both directions blocking access.
"LOCK" button Make sure that swing 9. Locked access pushed to lock access in Red LED of locked access in one panels are locked in one direction chosen direction ("A" or chosen direction is lit "B")* Both "LOCK" buttons to be Make sure that swing 10.
3 MAINTENANCE 3.1 General guidelines 3.1.1 Commissioning and subsequent maintenance of the turnstile to be performed only by the staff to be in charge of the turnstile.. 3.1.2 The turnstile to be serviced only by the staff having the relevant electrical safety qualification level according to the national requirements..
4 ROUTINE MAINTENANCE 4.1 General guidelines Minor malfunctions of the turnstile are listed in Table 9 and are remedied by the customer. More complicated malfunctions are remedied by the manufacturer’s representative. IMPORTANT: INSPECTION, CLEANING, REPAIR OF THE TURNSTILE COMPONENTS TO BE PERFORMED ONLY AFTER THE TURNSTILE DEENERGIZATION ! 4.2 Possible malfunctions Possible malfunctions of the turnstile and their remedies are listed in Table 9.
4.3. Adjustment of the zero position of leaf for “Sweeper- HG” 1. Press and hold RESET button (1) on the PCB.201.01.00.00 controller (Fig.18); 2. Set the glass leave (2) at the new zero position (manually close - Locked access) (Fig.17, Fig.18); Fig.
4.4 Postrepair checkout The turnstile performance is checked after repair according to paragraph 2.3.2 of this OM. 5 TRANSPORTATION AND STORAGE 5.1 Turnstile storage It is forbidden to subject the turnstile to jerks and impacts during storage. Transportation trolleys to be used for handling of the turnstile.
Annex B Control panel and connection diagram 1 – control panel housing ; 5 – "FREE ACCESS" mode control button; 2 – "SINGLE ACCESS" mode control button 6 – "PANIC" mode control button; 3 – front plate; 7 – access direction LED display; 4 –...
Page 31
Continued Annex B Control panel and connection diagram Figure B.2 – Connection diagram of control panel AUIA.114.02.00.00...
Annex C.1 Wiring diagram of the "SWEEPER-HG" type turnstile Sweeper-HG 2 Master/Slave AUIA 207 Rev. 2/MS Wi re s to ma ste r p a rt o f tu rn sti l e HL 4 PCB.2 0 5 .0 1 .0 5 .0 0 XS2 5 +1 2 V PCB 2 0 1 .0 1 .0 0 .0 0...
Annex C.2 Wiring diagram of the "SWEEPER-HG" type turnstile Sweeper-HG 1 Slave AUIA 207 Rev. 2/MS Wires to master part of turnstile PCB 201.01.00.00 XS19 XS20 XS21 XS22 XS23 XS24 IN 1 GRN 1 IN 2 RED 1 Жгут ? 2 IN 3 GRN 2 IN 4...
Annex D.1 Diagram of the turnstile connection to access control system (ACS) Relay 1 Relay 2 Door contact 1 Door contact 2 inp1 - "TO BE OPENED A" in pulse mode. When command is issued entry is activated for 5 sec. inp2- "TO BE OPENED B"...
Annex D.2 Diagram of the turnstile connection to access control system (ACS) inp1- " TO BE OPENED A" in pulse mode. When command is issued the input is activated for 5 sec. . inp - 2 " TO BE OPENED B" in pulse mode. When command is issued the input is activated for 5 seconds.
Annex D.3 Diagram of the turnstile connection to fire alarm (FA) inp1- " TO BE OPENED A" in pulse mode. When command is issued the input is activated for 5 sec. inp - 2 " TO BE OPENED B" in pulse mode. When command is issued the input is activated for 5 seconds.