15. Commissioning

Before commissioning the humidifier, check once again that all installation and wiring work has been carried
out correctly and fully completed. In particular, the water and power supply connections must be in proper or-
der and comply with the relevant safety regulations.

15.1 Manual functions

Release of permeat inlet into the humidifier
• Release of 230 V / 50 Hz to the transformer and
switch on transformer
Switch on humidifier (The control lamp lights up GREEN)
The SET humidity at the continuous control
must be higher than the ACTUAL humidity
Set set point higher than the ACTUAL humidity
40
No liability accepted for translation or printing errors. Subject to changes in dimensions, weights and other technical data.
All rights reserved. Modifications, reprints and photomechanical reproduction, even in extract from, require the express permission of BOGA GmbH, Werkstraße 16, D-59494 Soest.
Fig. 37 - Stop cock
Fig. 38 - Circuit breaker
Fig. 39 - ON/OFF switch
Fig. 40 - Continuous controller CT1
[MBA_UB-1...4-CT_3.1_EN] Rev.: 02/2022 Translation of the original instructions

Advertisement

Table of Contents
loading

Table of Contents