3.3 Fixing the cabinet

Unscrew 2x M6 nuts on front bottom roof side (see
Lift up roof, disconnect antenna cable (if present) and remove cabinet roof (see
Fix chains or straps (minimum length 1 meter) to all lifting lugs (see
move system to the desired position.
Use 4x M10 screw to fix cabinet to ground, correct torque depends on type of screws and material
of mounting base.
Put back cabinet roof, connect antenna cables (if present) and fix roof to cabinet with 2x M6 nuts.
!!! WARNING !!!
Do not use any other technique to lift the cabinet because of imminent damage.
Never lift cabinet with opened door.
Do not lift cabinet with installed modules and batteries.
Figure 3.4 Unmount cabinet roof
Installation Guide ● PowerShaper 2.0
22
Figure
3.4).
Figure 3.5 Disconnect antenna cable
Figure 3.6 Cabinet lifting
Mechanical installation
Figure
3.5).
Figure
3.6), securely lift and