Preparing Installation Site; Pre-Installation Steps - Pixii PowerShaper 2.0 Installation Manual

Grid tied energy storage system
Table of Contents

Advertisement

2 Preparing installation site

2.1 Pre-installation steps

1. Organize installation site
• Mounting base strong enough to carry weight of fully equipped system (approx. 950kg)
• Clearances for cabinet access
Front
Rear
Top
Sides
Between cabinets
(multi-cabinet installation)
NOTE:
It is strictly required to follow local regulations if separation distances larger than the table above are
required.
NOTE:
If the energy storage system is installed indoor, automatic sprinkler system is highly recommended
and sometimes required. Local regulations must be adhered to.
2. Prepare installation tools
• Use insulated tools suitable for electrical installations
• Recommended tools list is in chapter
3. Prepare AC Mains supply
Correct type of AC Mains supply (TN-S/ IT/TT)
Correct rating of AC input cables and external fuses
AC Mains supply meter
Installation Guide ● PowerShaper 2.0
Minimum distance
Fan Filter
Cabinet
Cabinet
with AC
80cm
5cm
30cm
25cm
5cm
20cm
"Tool" on page 8
Suggested distance
Fan Filter
Cabinet
Cabinet
with AC
100cm
25cm
90cm
60cm
25cm
35cm
Preparing installation site
17

Advertisement

Table of Contents
loading

Table of Contents