Tap STOP then switch the machine off.
l
The screen shows the trial run results in digits and as a vector in the polar diagram. The
arrow direction shows the path of the balancing run. In the trial run the residual imbal-
ance should reduce.
Tap NEXT to see hint for the trim run.
l
If imbalance reduces, keep the trial weight. If imbalance doubles, remove the trial
weight.
Continue to do a trial run with mass on plane A, then do a trial run with mass on plane B.
l
After the two trial runs carry out correction on both planes. Repeat the correction steps
until the balancing quality is less than 1 mm/s on all locations shown.